We have been working on this for almost 6 months.
We started grading in Oct. 07 and are now close to a concrete poor. Also, the building arrived last week.
40x60x16 CBC building
2/12 roof
2 ea. 14h X 12w roll-ups
1 ea. walk door
4 ea. windows
2 10' ridge vents
6 ea. sky lights
4'' insulation / sides and top
5.5'' pad
Moved 4000 cubic yards of dirt
400 tons of 3/4'' road base for road into site. (Need 200 tons more when project completed.) 3 weeks of grading and compacting. Lots of pizza for the work crew.
100 bales of straw / 1 bag of seed / 100+ feet of waddles.
Engineered plans for every step. Site plan / Grading / building / foundation etc.
Anyways check it out. I'll post more pics as the build continues.
We started grading in Oct. 07 and are now close to a concrete poor. Also, the building arrived last week.
40x60x16 CBC building
2/12 roof
2 ea. 14h X 12w roll-ups
1 ea. walk door
4 ea. windows
2 10' ridge vents
6 ea. sky lights
4'' insulation / sides and top
5.5'' pad
Moved 4000 cubic yards of dirt
400 tons of 3/4'' road base for road into site. (Need 200 tons more when project completed.) 3 weeks of grading and compacting. Lots of pizza for the work crew.
100 bales of straw / 1 bag of seed / 100+ feet of waddles.
Engineered plans for every step. Site plan / Grading / building / foundation etc.
Anyways check it out. I'll post more pics as the build continues.